Name of Project:  Concreting of Pedi-an Street at Purok Libertad, Poblacion, Sto Niño, South Cotabato – Phase 1 (213 Meters)

Source of Found: LDF 20%  CY 2021

Total Cost: 2,488,000.00

Date Started: May 27, 2021

Date  Completed: July 26, 2021

Project Status: Completed